My Power Projects
1. STREET-LIGHT PROJECTS:










2. POWER GENERATION PROJECTS
Afam Power Station(s):
A new 180 Megawatts Alstom Gas Turbine Engine Power Station at Afam-Phase 1 completed.

Trans Amadi:
Phase II (GE Turbines) – 100 Megawatts: Completed and commissioned.
Phase I (Solar Turbines) – 36 Megawatts: Overhauled engines to bring available energy to 36MW. 
Eleme - Upgrading from 20 - 75 MW
Provision/installation of the following:
2x1275 Generating sets at the Rivers State University of Science and Technology
2/2000KVA Generating sets at the Rivers State University of Science and Technology
1x1275KVA Generating Set at Podium Block, State Secretariat Complex
2x1500KVA Generating Set at Blocks A, B and C, State Secretariat Complex
1x1500KVA Generating Set at Point Block, State Secretariat Complex
7.5MVA Injection Sub-Station Transformer at Abana Street to Supply and Stabilize
Power at Government House and the State Secretariat Complex
3. POWER DISTRIBUTION:
Transformers Provided/Installed:

200 Distribution Transformers of various sizes ranging from 200KVA to 500KVA deployed to various parts of the State.
408 additional Distribution transformers Commissioned.
5 No. 33/11kv Injection sub-stations at School of Nursing (2x2.5MVA)
COE (2x2.5MVA)
Borokiri (1x7.5MV)
Abuloma (1x7.5MVA)
Woji (1x15MVA)
Construction of additional 28 No.of Secondary Injection Sub-stations
4. INTERVENTION/ASSISTANCE TO PHCN-TCN:
1x15MVA at PH Mains, Oginigba.
1x15MVA at PH Town, Nzimiro
2 sets of 9-Panel 11kv Board
2 No. 33kv Breaker
Construction of 33kv Line from Oginigba to Bori
5. TRANSMISSION PROJECTS
2.5 MVA 0.416/11KV Step-up Power Transformer Installed at the Buguma Power Station Asari Toru L.G.A.

Construction of 132KV Terminal Transmission Towers

3x60MVA 132/33kv transformer-TCN Oginigba and Afam Power Stations; outstanding with RE
Construction of 4x60MVA 132/33kv Transmission Station- TCN Oginigba
Construction of 2x60MVA 132/33kv Transmission Station at Elelenwo
Afam to Elelenwo 132kv DC Transmission Line (on-going)
132kv Turn In-Turn Out construction at Afam
132kv Turn In-Turn Out construction at Oginigba
132kv Triple Circuit Transmission Line from Trans Amadi Power Station to PH Mains, Oginigba
Omoku to Ndoni 132kv DC Transmission Line
Afam to Onne and Emohua to Rumuolumeni 132kv DC Transmission Lines and construction 2x40MVA
132/33kv Transmission Sub-Stations (Proposed by Power Distribution Committee).
6. RURAL ELECTRIFICATION PROJECTS:
Akwa Rural Electrification Scheme

Abua Central in Abua/Odual LGA, for the first time in history is connected to the national grid by the Ministry of Power through the installation of 3 x 2.5MVA sub-Injection Transformer and 7 distribution transformers and TDN (Governors intervention).
The communities are Ayama, Okana, Ogbema, Omokwa, Odaga, Otari, Emilaghan, among others.
33kv Transmission Line from Ahoada East to Ogonokom in Abua-Odua L.G.A

Ahoada East L.G.A
Odiabidi,
Okporowo,
Obele, etc have all been electrified, as well as Edeoha, in collaboration with NDDC
Etche L.G.A
Akwa
Ukakwo
Umiocha, etc
Abonnema, Buguma & Opobo Town
2 x 2MVA caterpillar Diesel Gen. Set have been installed to run alternately and provide stable power supply in these major and ancient towns.